Saad Mohammadi, CEO of "Mines" at the news conference: 2. The steel in the production of sponge iron is one of our projects, which is about 2.9 % improvement. 4. We have a 5.5 % physical progress in the construction of the steel smelting plant, we have a 5.5 % physical progress in the pelletization plant, our solar power plant is currently 2 % progress, the Semnan power plant ended in the next six months and its investment has become production. Ardebil Steel has improved by 4.9 %, and Euclid steel has just begun, nearly 2 % progress. @Bourse24ir